
UNIVERSITY OF BRADFORD
School of Engineering, Design and Technology
PROJECT EVALUATION REPORT FOR
THE
‘*unconfirmed*’
A RECYCLING COLLECTION AND
COMPACTION FACILITY
Tom Tidswell
BSc (Hons) Industrial Design
Main
Project Supervisor: Mr Nik Hills
Stage
3 BSc Major Design Project
2006
- 2007
Contents
Contents 1
Introduction. 2
Method and Process 3
Techniques and Skills 3
Planning. 4
Proposal 5
Final Solution. 5
Conclusion. 7
Appendices 8
This report evaluates the complete progress of the author’s
final year project. Contained in this report are criticisms of project
handling, evaluations of timekeeping methodology and planning, and an overview
of lessons learned.
The author aims for the report to be succinct and honest,
and will not stop short of personal criticism where necessary.
Retrospectively, this entire module has been a massive
learning exercise. From the outset, it was this author’s opinion that his
existing knowledge of the design method and process were more than adequate to
complete the module satisfactorily. This however did not turn out to be the
case. As the design process is an ongoing tool for the designer, there is very
clear evidence (from the completed journal) that there was a marked improvement
in its understanding and application.
It is unfortunate that the lack of understanding was not
realised earlier, as its effect was ultimately to delay the progress of the
work. Unrelated to this task was an assignment in a different module (Studio
Mentoring), which served as a sharp realisation of this situation.
As noted previously, there was a clear difference between
design process use at the beginning and end of the project. This difference, it
seems, manifested itself in the designer’s increasing ability to commit his
thoughts to paper. Whereas initially care and attention was paid to each sketch
or note on a page; ultimately, effort was refocused onto inspiration and
contribution to the journal. Consequently, when this truth was realised there
was an increase in creativity, and the designer was amazed at the constant flow
of ideas.
After completion, looking over the finished work, it is
painstakingly obvious that process knowledge was absent, and the actual
methodology followed was akin to ‘blundering in the dark’. As uncomfortable as
this may sound for a project of this importance, the design method was
ultimately implemented, and has resulted in a perfectly sound product.
There have been many points at which the design process has
been used to point out weaker ideas that were not initially obvious. If the
designer had been more fluent with the process, this may have happened in a
more timely fashion. This technique of weeding out inferior ideas, expanding
them, and then contracting them again was repeated numerous times, explaining
why there have been so many changes along the path to the final design. It is
the designer’s opinion that this is the reason why the solution is successful.
If the designer were in the position to restart the project,
it would be expected that a very similar set of conclusions would be reached.
The timescale would be definitely different, with more time freed for the
latter portions of the project.
Being inefficient in some areas of the design process was to
some extent alleviated by the quantity of work done in the middle portions of
the project (December/January). By no means is this an example of quantity over
quality, but the amount of work served as a ‘stream of consciousness’, and when
evaluating the completed work this meant no important elements were omitted.
This author’s skills definitely lie in his method of
production of computer models. Even though collectively the final year students
were advised against computer modelling in favour of GDL’s
(general design layouts), many more computer models were constructed than GDL’s. A GDL’s inherent
usefulness however was not overlooked, and so the computer models when created
were constructed to be manipulated later. Each time new inspiration occurred,
or change was needed, the model could be quickly altered then printed for
commenting. This methodology, in the author’s opinion, initially consumed more
time per model, but for each change (where a new GDL would be needed) there was
a time saving.
Over the course of the project approximately 100 different
computer models, some rough, some detailed, were constructed. Not all of these
were of direct use, but all allowed the designer to visualise some portion of
the design.
Where the designer’s skills fell short, effort was made to
reach a satisfactory conclusion. Research was an area where a more structured
approach would have been of huge benefit. For example, if research had been conducted
in more depth into basic conceptual areas such as ‘boxes’ or ‘storage’ in the
beginning, huge amounts of time could have been saved. Of course, it could be
argued that one needs to have travelled a train of thought to know it is not
suitable; however, with experience it could also be argued that instinct should
play a large part in these matters. Whatever the outcome of this project, it is
definitely true that the designer is now in a better position for beginning
further ventures.
It is a problem to note the designer’s lack of commitment at
some key points during this assignment. This is not implying that the project
was regarded apathetically, but just indicates the overwhelming pressure such a
project bestows upon the designer. This has devastated the planning of the
project, as it is inevitable such feelings arise when pressure is released by
being ‘on schedule’.
It is inevitable then that lack of commitment would lead to
slipping deadlines, but it should be noted that by no means is the author
offering it as an excuse.
At two points during the project, the time plan was
completely revised – due to changing attention required by different portions
of the design. That noted, the designer almost met his
personal deadlines for the entire project – only occasionally slipping behind.
If the opportunity to restart the project were to arise, a
concrete plan would be created first. The time plan would be then exploited as
a check not only for timekeeping, but also for gauging the amount of attention
a particular problem should be given (and hence not wasting time). On too many
occasions during the project it was realised focus had been placed on an
irrelevant problem.
During the development of this product, the requirements
stipulated in the project proposal were always kept in mind. Strictly, whilst
one of the targets was not met, the designer considers the product to be a
success; this is because of the proximity the final design is to meeting its
requirements. The costing of the final product is wrong when compared to the
proposal; costing less than half the stipulated price for manufacture and
retailing at around £100, where the proposal asked for £210-£250.
This decision to halve the manufacturing price was
deliberate. It was decided during development that the quoted price was too
high for a council to pay for such a unit, and so was lowered. With the
quantities involved in this instance, the retail price could be lowered even
further. One of the wishes for the product was met to a certain degree –the
waste would be the volume of one kerbside bin, just not placed inside.
Concerning the cleaning of the waste, that wish had to be disregarded because
of practicality and costing.
Specific challenge
The solution needs to
integrate with the existing recycling system, whilst suggesting a simplified
solution to the existing problem of multiple wheelie bins on a driveway.
Most important wants
1 Who will buy the product? – Wealthy adults with a large
kitchen and green lean
Who will use the product? – Everyone in the household
of the above
2 Target manufacturing price: £20-50
Designed retail price: £210-250 (rough price of three
wheelie bins)
3 Production quantity
–?
4 Must accept all council collected recyclable waste
5 Must fit into the kitchen. must
allow for different design tastes used in kitchen design
6 Some households have two or more wheelie bins outside
for recycling; this system should be able to hold and compact this into one
small bin for a week
7
As a premium product, ease of use is crucial
Most important wishes
1 Aim for a recycling system where all recycling is
placed in one kerbside bin
2 Cleaning of the waste before collection
In retrospect, this project proposal was so broad that the
solution could have met its requirements and been vastly different. This
actually brings more problems than benefits, as it is left up to the designer to
decide on specifics (which would only rarely happen in industry). Therefore, if
the exercise were to be repeated, the designer would initially supply a much
more restrictive proposal.
At the time of writing, some key features of the project
are incomplete. The designer is unhappy with the status of the following
aspects of the design:
· The material to be used for the internal boxes is still
uncertain (at the time of writing, tests are underway to evaluate materials
against others).
· There are some important safety features requiring much
greater definition (currently only a handful of sketches)
· The add-on (as the decision has been made for it to be) for
tin cans has no more than a rough definition
· Design
for manufacture and assembly has been kept in mind throughout the project, but
its definition remains to be committed to paper
The designer is happy with the following aspects of the
design:
· The costing has been a focus for the project, and a product
has been defined which makes economic sense
· The quality of the modelling throughout the project has been
high
· The justifications for the technology used are sound
· The product capitalises on simple low cost technology, and
does not have unnecessary complications
· The contemporary styling of the product is an achievement
for the price break intended
As a solution to a problem, the design works very well. It
would be more appropriate to comment on a more completed version of the design,
as there may be issues which only the final detailing will bring to
light.
To conclude, the final design is as it is thanks to the
improvements the designer has made to his application of the design process.
Whereas the design may be incomplete, the final stages of the product’s design
show a competent solution. The design would be nearer completion had the set of
plans been more strictly adhered to. Additionally, more appropriate blanket
research was needed to begin with – rather than just paying it lip service, as
this could have been used as a shortcut to a solution, which in reality took
longer to reach.
Initially, there were several key design processes
unfamiliar to the designer. As previously stated, the project has been a
massive learning exercise, and the designer notes the learning undertaken
during the project equips him well for similar situations in the future. The
new appreciation of time planning, self-discipline and initial research contributes
to improved future capabilities.
Appendices
APPENDIX
A
Major
Design Project Approval Form
|
Issue
Number: 5
Project
Title: *unconfirmed*
Recycle Waste Collector
|
Name:
Tom Tidswell
Date
Submitted: 03/10/06
Contact
No: 07841403961
|
Summary
of Product
|
A
collection facility to collect waste in the kitchen, under the worktop. A
premium product, to do to the ordinary waste bin what the dishwasher did for
the sink. It needs to fit, and perform perfectly in this environment.
Specific
Challenge
The
solution needs to integrate with the existing recycling system, whilst
suggesting a simplified solution to the existing problem of multiple wheelie
bins on a driveway.
|
Most
Important Wants
|
1
|
Who
will buy the product? – Wealthy adults with a large kitchen and green lean
Who
will use the product? – Everyone in the household of the above
|
|
2
|
Target
manufacturing price– £20-50
Designed
retail price – £210-250 (rough price of three wheelie bins)
|
|
3
|
Production
quantity –
|
|
4
|
Must
accept all council collected recyclable waste
|
|
5
|
Must
fit into the kitchen
Must
allow for different design tastes currently used in kitchen design
|
|
6
|
Some
households have two or more wheelie bins outside for recycling; this system
should be able to hold and compact this into one small bin for a week
|
|
7
|
As
a premium product, ease of use is crucial
|
Most
Important Wishes
|
a
|
Aim
for a recycling system where all recycling is placed in one kerbside bin
|
|
b
|
Cleaning
of the waste before collection
|